Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 17 tasks across 4 phases, about 19 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Design | Space planning and test fit | 10 days | Day 1 | Nothing (starts first) |
| Design | Design development | 15 days | Day 11 | Space planning and test fit |
| Design | Landlord design approval | 10 days | Day 26 | Design development |
| Design | Permit application | 20 days | Day 36 | Landlord design approval |
| Design | Order furniture | 5 days | Day 56 | Permit application |
| Build | Demolition and strip-out | 5 days | Day 61 | Order furniture |
| Build | Partitions and framing | 10 days | Day 66 | Demolition and strip-out |
| Build | MEP and fire protection rough-in | 12 days | Day 76 | Partitions and framing |
| Build | IT and AV cabling | 5 days | Day 88 | MEP and fire protection rough-in |
| Build | Ceilings | 7 days | Day 93 | IT and AV cabling |
| Finish | Paint and wall finishes | 7 days | Day 100 | Ceilings |
| Finish | Flooring | 7 days | Day 107 | Paint and wall finishes |
| Finish | Joinery and kitchenette | 7 days | Day 114 | Flooring |
| Finish | Furniture delivery and install | 5 days | Day 121 | Joinery and kitchenette |
| Handover | Inspections and sign-off | 3 days | Day 126 | Furniture delivery and install |
| Handover | Punch list | 5 days | Day 129 | Inspections and sign-off |
| Handover | Handover | 1 day | Day 134 | Punch list |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this commercial office fit-out
Office fit-outs add a step residential projects don't have: landlord approval of the design, often before permits can be filed. This schedule includes it, along with ceilings, IT cabling and furniture, which often has long lead times.
Pair it with the office move template if your team is relocating into the space.
Who it's for: Facilities managers, fit-out contractors, project managers and tenants.
How to use it
- Open the plan. Click Use this template.
- Start long-lead orders early. Unlink the furniture order so it starts during design. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Add landlord rules. Add rows for after-hours work windows or freight elevator bookings if the building requires them.
- Share with stakeholders. Send a read-only link to the landlord, contractor and internal team.
Planning tips
- Ask the landlord about their approval process at the start.
- Coordinate IT cabling before ceilings close.
- Confirm furniture lead times when ordering.
Frequently asked questions
- What is a fit-out?
- The work to make a commercial space ready for a tenant: partitions, services, finishes and furniture.
- Can I plan multiple floors?
- Yes. Duplicate the build and finish rows per floor.
- Is it free?
- Yes. Opening and editing the template is free.
Related templates and guides
- 3-Week Look-Ahead Schedule Gantt chart template
- Office Move Plan Gantt chart template
- Construction Schedule Gantt chart template
- IT Network Upgrade Gantt chart template
- Construction scheduling with a Gantt chart
- Microsoft Project alternative for schedules
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.