Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 13 tasks across 5 phases, about 14 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Book | Select show and book booth space | 7 days | Day 1 | Nothing (starts first) |
| Book | Set goals and budget | 3 days | Day 8 | Select show and book booth space |
| Design | Booth design and graphics | 21 days | Day 11 | Set goals and budget |
| Design | Collateral and giveaways | 14 days | Day 32 | Booth design and graphics |
| Design | Demo setup | 7 days | Day 46 | Collateral and giveaways |
| Logistics | Exhibitor services orders | 3 days | Day 53 | Demo setup |
| Logistics | Ship to advance warehouse | 5 days | Day 56 | Exhibitor services orders |
| Logistics | Travel and badge registration | 3 days | Day 61 | Ship to advance warehouse |
| Promote | Pre-show outreach and meeting booking | 21 days | Day 64 | Travel and badge registration |
| Promote | Staff briefing | 1 day | Day 85 | Pre-show outreach and meeting booking |
| Show | Show days | 3 days | Day 86 | Staff briefing |
| Show | Lead follow-up | 10 days | Day 89 | Show days |
| Show | Show results review | 2 days | Day 99 | Lead follow-up |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this trade show plan
Exhibiting at a trade show is mostly deadline management: booth space, the exhibitor services order deadline, advance warehouse shipping and badge registration all close before the show, and late orders commonly cost more.
This plan is written from the exhibitor's side for a single show.
Who it's for: Event marketers, field marketers and sales teams exhibiting at a show.
How to use it
- Open the plan. Click Use this template.
- Enter the organizer's deadlines. Add the exhibitor manual's deadlines as milestones and line tasks up before them.
- Start outreach early. Unlink pre-show outreach so meetings are booked weeks in advance. In the task panel, remove the predecessor, then set the new start date. Then check that the task that came next still lists the earlier work as a predecessor, so delays keep cascading.
- Share with the booth team. Send a read-only link to everyone staffing the booth.
Planning tips
- Read the exhibitor manual on day one; it lists every deadline.
- Agree who owns lead follow-up before the show.
- Keep a list of shipped items to check on arrival and for return shipping.
Frequently asked questions
- How early should I plan for a trade show?
- Ideally several months ahead, especially for custom booth graphics. This template spans about three months.
- Can I plan several shows in a year?
- Yes. Save one project per show on Solo, or add a lane per show.
- Is there a template for conference organizers?
- Yes. The conference planning template is written for organizers.
Related templates and guides
- Conference Planning Timeline Gantt chart template
- Marketing Launch Plan Gantt chart template
- Event Planning Timeline Gantt chart template
- Event planning timeline
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.