Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 14 tasks across 4 phases, about 4 weeks from start to finish with the parallel work shown.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Week 1 | Kickoff and scope confirmation | 1 day | Day 1 | Nothing (starts first) |
| Week 1 | Research and inputs | 4 days | Day 2 | Kickoff and scope confirmation |
| Week 1 | Week 1 check-in | 1 day | Day 6 | Research and inputs |
| Weeks 2-3 | First draft or build | 8 days | Day 7 | Week 1 check-in |
| Weeks 2-3 | Supporting materials | 5 days | Day 7 | Week 1 check-in |
| Weeks 2-3 | Week 2 check-in | 1 day | Day 12 | Supporting materials |
| Weeks 2-3 | Week 3 check-in | 1 day | Day 15 | First draft or build |
| Weeks 4-5 | Review round with stakeholders | 3 days | Day 16 | Week 3 check-in |
| Weeks 4-5 | Revisions | 5 days | Day 19 | Review round with stakeholders |
| Weeks 4-5 | Week 4 check-in | 1 day | Day 19 | Review round with stakeholders |
| Weeks 4-5 | Week 5 check-in | 1 day | Day 24 | Revisions |
| Week 6 | Final approval | 2 days | Day 25 | Week 5 check-in |
| Week 6 | Delivery and handover | 2 days | Day 27 | Final approval |
| Week 6 | Retrospective | 1 day | Day 29 | Delivery and handover |
Durations are examples to replace with your own estimates, not benchmarks. Some work runs in parallel, so the plan takes 29 days instead of the 36 it would take one task at a time. The 11 darker bars are the critical path: a day lost on any of them moves the finish date.
About this weekly project plan
A weekly Gantt chart is the most useful view for a team doing the work: it is short enough to see every task and long enough to show what is coming. This template plans a six-week project with weekly check-ins as milestones, so progress is reviewed at a fixed rhythm instead of whenever someone remembers.
It suits a short internal project, a sprint of related work across several people, a client engagement or the current quarter's slice of a larger plan. Tasks are sized from one day to two weeks, which is the range a weekly chart shows clearly.
For longer plans, keep the year in the monthly project plan template and use this one for the next six weeks of detail.
Who it's for: Team leads, consultants and small teams running short projects with a weekly rhythm.
How to use it
- Use this template. Click Use this template. Six weeks of work open as a Gantt chart grouped by week, with the check-ins already placed.
- Fill in the real tasks. Rename the placeholder tasks with your project's work. Keep each task within one or two weeks so it fits the weekly view.
- Align the check-ins. Move the check-ins to the day your team actually meets each week. Tasks linked to them stay in order.
- Update weekly. At each check-in, update progress on the bars and send a fresh read-only link instead of writing a status email.
Why weekly check-ins are on the chart
A check-in that is not on the plan is easy to skip. Here each week ends with a one-day check-in, and the next block of work waits for it. That makes the review a real gate: the first draft does not start until the research has been checked, and the revisions do not start until stakeholders have reviewed.
Supporting materials run beside the first draft in weeks two and three, so the people producing them are not idle while the main piece of work is built. That overlap is why the plan fits into six weeks.
Turning it into a weekly status report
Once the plan is in the editor, the Weekly status button builds a short report of what is done, what is in progress, what is at risk and what falls in the current week. Bring it to each check-in and the meeting can focus on decisions instead of collecting updates.
Planning tips
- Hold the check-in on the same day each week.
- If a task is longer than two weeks, split it so each part ends at a check-in.
- Keep a short buffer in week 6. Final approvals often take longer than planned.
- Use the retrospective to adjust the template for your next project.
Frequently asked questions
- What is a weekly Gantt chart?
- A Gantt chart where the timescale is shown in weeks and tasks are sized in days or a couple of weeks. It is the usual view for a team planning the next month or two of work.
- Can I change the plan length?
- Yes. Add weeks by adding tasks and check-ins after week 6, or delete the middle weeks for a shorter plan.
- Can I see the plan as a calendar or a board?
- Yes. The same plan can be shown as a Gantt chart, a timeline, a Kanban board, a calendar or a dashboard, and changes in one view show in all of them.
- Does my team need accounts?
- No. Anyone can open a read-only share link. A free account saves one project; Solo ($12/month) adds unlimited projects and downloads.
Related templates and guides
- Simple Project Plan Gantt chart template
- 12-Month Project Plan Gantt chart template
- Software Sprint Plan Gantt chart template
- Content Marketing Plan Gantt chart template
- Smartsheet alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.