Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 11 tasks across 4 phases, about 39 weeks from start to finish with the parallel work shown.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Q1 Set up | Goals, budget and team | 30 days | Day 1 | Nothing (starts first) |
| Q1 Set up | Detailed planning and procurement | 30 days | Day 31 | Goals, budget and team |
| Q1 Set up | Q1 review | 1 day | Day 61 | Detailed planning and procurement |
| Q2 Delivery wave 1 | Wave 1 delivery | 60 days | Day 62 | Q1 review |
| Q2 Delivery wave 1 | Wave 1 pilot and feedback | 30 days | Day 122 | Wave 1 delivery |
| Q3 Delivery wave 2 | Wave 2 delivery | 60 days | Day 122 | Wave 1 delivery |
| Q3 Delivery wave 2 | Communications and training plan | 30 days | Day 62 | Q1 review |
| Q3 Delivery wave 2 | Mid-year review | 1 day | Day 152 | Wave 1 pilot and feedback |
| Q4 Rollout and review | Organisation-wide rollout | 45 days | Day 182 | Wave 2 delivery, Communications and training plan, Mid-year review |
| Q4 Rollout and review | Benefits measurement | 30 days | Day 227 | Organisation-wide rollout |
| Q4 Rollout and review | Annual review and next-year plan | 14 days | Day 257 | Benefits measurement |
Durations are examples to replace with your own estimates, not benchmarks. Some work runs in parallel, so the plan takes 270 days instead of the 331 it would take one task at a time. The 8 darker bars are the critical path: a day lost on any of them moves the finish date.
About this 12-month project plan
Some plans are about months, not days: an annual programme, a year-long improvement project, a grant-funded initiative or a yearly departmental plan. A monthly Gantt chart shows the big blocks of work, the quarterly milestones and the hand-offs between them, so a board or sponsor can read the year on one screen.
This template covers twelve months in four quarters: set-up, delivery in two waves, rollout and review. Durations are in days so the editor can schedule them precisely, but each task is sized in whole months (about 30 days) so the chart reads as a monthly plan.
Use it as the top level of a large plan. When a quarter starts, add the detailed tasks for that quarter underneath, or plan them in a separate project using one of the shorter templates.
Who it's for: Programme managers, department heads and anyone presenting an annual plan to a board, funder or leadership team.
How to use it
- Use this template. Click Use this template to open the twelve-month plan. Each quarter is a lane, so the chart reads left to right like a calendar year.
- Set the start month. Set the first task to the first day of your plan year. All later tasks move with it.
- Rename the waves. Replace the two delivery waves with your own workstreams or phases. Keep the link from wave 1 to wave 2 if the second wave reuses what the first one built.
- Present it. Share a read-only link with your board or sponsor. Recipients do not need an account.
Reading a monthly Gantt chart
On a monthly chart, every bar is at least a few weeks long and the milestones mark the end of each quarter or review. The detail that matters is the order: what has to be in place before the next block of work can start. Here the second delivery wave starts when the first wave's delivery finishes, while the pilot and feedback for wave 1 run alongside it. The mid-year review sits between the pilot and the rollout, so the decision to roll out is made with real feedback.
Communications and training run from the second quarter in parallel with delivery, which keeps them off the critical path but makes sure they are ready for the rollout.
Monthly plan or weekly plan?
If the people reading the plan care about the year, use months. If they care about the next six weeks, use the weekly project plan template. Many teams keep both: a monthly chart for leadership and a weekly chart for the team doing the current quarter's work.
Planning tips
- Mark each quarter's review as a milestone so it is never quietly skipped.
- Keep budget decisions in the first quarter; procurement in a later quarter is a common reason annual plans slip.
- Measure benefits after the rollout, not during it, and put that measurement on the plan.
- Start next year's planning before this year ends; the annual review task leaves two weeks for it.
Frequently asked questions
- What is a monthly Gantt chart template?
- A Gantt chart whose tasks are sized in months, usually covering a full year. It shows the main phases, quarterly milestones and dependencies without day-to-day detail.
- Can I show quarters on the chart?
- Yes. This template uses one lane per quarter, so each quarter's work is grouped together and the chart reads like a calendar year.
- Can a plan run longer than a year?
- Yes. The editor handles plans of up to two years. Add tasks past the twelfth month and the chart extends.
- Is there a spreadsheet version?
- Download CSV on this page gives you the plan with dates and dependencies, ready for Excel or Google Sheets.
Related templates and guides
- Simple Project Plan Gantt chart template
- Strategic Planning Process Gantt chart template
- Annual Budget Planning Gantt chart template
- Weekly Project Plan Gantt chart template
- Smartsheet alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.