Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 18 tasks across 6 phases, about 13 weeks from start to finish with the parallel work shown.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Initiate | Business case and sponsor approval | 5 days | Day 1 | Nothing (starts first) |
| Initiate | Project charter and RACI | 3 days | Day 6 | Business case and sponsor approval |
| Requirements | Current state assessment | 6 days | Day 9 | Project charter and RACI |
| Requirements | Business and technical requirements | 8 days | Day 15 | Current state assessment |
| Requirements | Security and compliance requirements | 4 days | Day 15 | Current state assessment |
| Procure | Vendor shortlist and demos | 8 days | Day 23 | Business and technical requirements |
| Procure | Vendor selection and contract | 10 days | Day 31 | Vendor shortlist and demos, Security and compliance requirements |
| Build | Solution design | 6 days | Day 41 | Vendor selection and contract |
| Build | Environment provisioning | 5 days | Day 47 | Solution design |
| Build | Configuration and integration | 15 days | Day 52 | Environment provisioning |
| Build | Data migration rehearsal | 5 days | Day 67 | Configuration and integration |
| Test | System and integration testing | 8 days | Day 67 | Configuration and integration |
| Test | User acceptance testing | 6 days | Day 75 | System and integration testing, Data migration rehearsal |
| Test | Training materials and sessions | 6 days | Day 75 | System and integration testing |
| Deploy | Change advisory board approval | 2 days | Day 81 | User acceptance testing |
| Deploy | Cutover and go-live | 2 days | Day 83 | Change advisory board approval, Training materials and sessions |
| Deploy | Handover to operations and service desk | 3 days | Day 85 | Cutover and go-live |
| Deploy | Post-implementation review | 3 days | Day 88 | Handover to operations and service desk |
Durations are examples to replace with your own estimates, not benchmarks. Some work runs in parallel, so the plan takes 90 days instead of the 105 it would take one task at a time. The 15 darker bars are the critical path: a day lost on any of them moves the finish date.
About this it project plan
IT projects have two audiences: the business that wants the new system and the operations team that will have to run it. Plans written for only one of them miss work. This template covers both, from the business case and requirements through vendor selection, build and testing, to change approval, cutover and a proper handover to operations.
It suits a rollout of a new business application, a major upgrade, or an infrastructure change that users will notice, delivered over about four months by an internal IT team with a vendor or integrator.
For specific project types there are tighter templates: network upgrade, cloud migration, CRM and ERP implementation and data migration. Use this one when your project does not fit any of those or when you need a plan to win approval before the details are known.
Who it's for: IT project managers, IT managers and PMO leads who need a defensible plan for a system rollout.
How to use it
- Use this template. Click Use this template. The plan opens with each phase as a lane and the approval gates linked, so the critical path through procurement and testing is visible straight away.
- Fit procurement to your rules. Procurement timelines vary more than anything else in IT projects. Replace the vendor tasks with your organisation's real purchasing steps and lead times.
- Book the change window. Set the cutover task on your agreed change window, then check that testing and training finish before it.
- Report weekly. Update progress on each bar and share the read-only link, or use the weekly status view, for the steering group.
Approval gates in an IT project
Three gates shape this plan: sponsor approval of the business case, vendor contract signature, and change advisory board (CAB) approval before cutover. Each is a task with a duration because each needs a meeting that someone else schedules. Treat their durations as lead times, not effort.
Security and compliance requirements run beside the business requirements and both feed the vendor decision. Projects that add security review after the contract is signed often discover a requirement the chosen product cannot meet.
Handover is part of the project
The plan does not end at go-live. Handover to operations and the service desk covers runbooks, monitoring, support contacts and known issues. Without it, the project team becomes the support team by default, and the next project starts late.
Planning tips
- Rehearse the data migration at least once before user acceptance testing, using a copy of production data where your policies allow it.
- Train users close to go-live; training given a month early is mostly forgotten.
- Name a single owner for the cutover runbook, and keep the rollback steps in the same document.
- Keep the post-implementation review short and on the plan, so lessons are captured while people remember them.
Frequently asked questions
- What are the phases of an IT project plan?
- A typical IT project moves through initiation, requirements, procurement (if you buy), build or configuration, testing, deployment and handover. This template includes all of these with the approval gates between them.
- How do I show a change freeze or change window?
- Add a task for the freeze period in the deploy lane, or set the cutover task's start date to your agreed window. Dependencies make sure nothing that must happen first is scheduled after it.
- Can I import an existing plan from Microsoft Project?
- Yes. The editor imports Microsoft Project XML files with tasks, dates and links. The Project Online alternative page explains the steps.
- Is this suitable for an infrastructure project?
- Yes, with the vendor tasks shortened if you already have a supplier. For network-specific work, the network upgrade template has more detailed tasks.
Related templates and guides
- Implementation Plan Gantt chart template
- IT Network Upgrade Gantt chart template
- Cloud Migration Plan Gantt chart template
- ERP Implementation Plan Gantt chart template
- Data Migration Plan Gantt chart template
- Sprint planning on a Gantt chart
- Microsoft Project alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.