Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 17 tasks across 5 phases, about 9 weeks from start to finish with the parallel work shown.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Plan | Campaign brief and goals | 3 days | Day 1 | Nothing (starts first) |
| Plan | Audience and channel plan | 4 days | Day 4 | Campaign brief and goals |
| Plan | Budget sign-off | 2 days | Day 8 | Audience and channel plan |
| Creative | Key message and copy | 6 days | Day 8 | Audience and channel plan |
| Creative | Design and visuals | 8 days | Day 14 | Key message and copy |
| Creative | Creative review and approval | 3 days | Day 22 | Design and visuals |
| Build | Landing page | 6 days | Day 25 | Creative review and approval |
| Build | Tracking and UTM setup | 2 days | Day 31 | Landing page |
| Build | Email sequence build | 4 days | Day 25 | Creative review and approval |
| Build | Ad sets and targeting | 3 days | Day 25 | Creative review and approval, Budget sign-off |
| Run | Campaign launch | 1 day | Day 33 | Tracking and UTM setup, Email sequence build, Ad sets and targeting |
| Run | Paid media flight | 21 days | Day 34 | Campaign launch |
| Run | Email sends | 14 days | Day 34 | Campaign launch |
| Run | Organic social posts | 21 days | Day 34 | Campaign launch |
| Run | Mid-flight optimisation | 2 days | Day 34 | Campaign launch |
| Report | Results analysis | 4 days | Day 55 | Paid media flight, Email sends, Organic social posts |
| Report | Results report and learnings | 2 days | Day 59 | Results analysis |
Durations are examples to replace with your own estimates, not benchmarks. Some work runs in parallel, so the plan takes 60 days instead of the 106 it would take one task at a time. The 12 darker bars are the critical path: a day lost on any of them moves the finish date.
About this marketing campaign plan
Campaigns run late in the approval loop. Copy goes back and forth, design waits for copy, and paid media waits for both, so a two-day delay on the brief becomes a two-week delay on launch. This template makes the approval gate explicit and lets each channel start as soon as its own inputs are ready.
It covers one integrated campaign over about eight weeks: paid search and social, an email sequence, organic social and a landing page, with tracking set up before anything goes live and a results report at the end.
Use it for a seasonal promotion, a lead-generation campaign or a webinar push. For an always-on content programme, the content marketing calendar template fits better.
Who it's for: Marketing managers, campaign leads and agencies running a campaign across several channels.
How to use it
- Use this template. Click Use this template to open the campaign as a live Gantt with planning, creative, build, run and reporting as lanes.
- Set the launch date. Drag the campaign launch to your date. The creative and build tasks show how much time you really have for approvals.
- Shorten or add channels. Delete the channels you are not using and add any you are, such as a webinar or a partner newsletter. Link each new channel to the creative approval so it cannot start early.
- Track the flight. Update progress on the paid, email and social bars each week and send stakeholders a fresh read-only link instead of screenshots.
Why creative approval is the gate
Every channel in this plan waits for the creative review and approval task. That is deliberate. When paid ads, email and the landing page each start from their own draft of the message, the campaign launches with three versions of the offer. One approval gate keeps the message consistent and makes the cost of a late approval visible: drag it a few days to the right and watch the launch move.
Tracking setup waits for the landing page and the launch waits for tracking. A campaign that launches without working UTM tags cannot be measured, and the results report at the end becomes guesswork.
Running and reporting
The run lanes overlap: paid, email and organic social run in parallel for three weeks, with a short mid-flight optimisation task a few days in. Results analysis waits for all three channels to finish, so the report compares like with like. If your campaign has a hard end date (a sale or an event), make the paid flight end on that date and let the report follow it.
Planning tips
- Book approvers' time when you build the plan. The review task is short only if the reviewer is available.
- Keep the budget sign-off linked to the ad set build so nobody spends before the budget exists.
- Add a test send to the email sequence task, and a test conversion to the tracking task.
- Write down what success looks like in the brief, so the results report has something to measure against.
Frequently asked questions
- What should a marketing campaign Gantt chart include?
- The brief and goals, audience and channel plan, creative production and approval, the build for each channel, the launch, the in-flight period for each channel and a results report. This template includes all of them with the dependencies between them.
- How long does a marketing campaign take to plan?
- For an integrated campaign like this one, four to five weeks of planning and production before launch is common, then a few weeks in flight. Replace the example durations with your team's real turnaround times.
- Can I use this for a single-channel campaign?
- Yes. Delete the channels you do not need. The plan, creative and report lanes still apply.
- Is there a related timeline view for campaigns?
- Yes. The marketing campaign timeline page explains how to present the same plan as a timeline for stakeholders, and the content marketing calendar template covers ongoing publishing.
Related templates and guides
- Marketing Launch Plan Gantt chart template
- Content Marketing Plan Gantt chart template
- Social Media Campaign Plan Gantt chart template
- Product Launch Plan Gantt chart template
- Marketing campaign timeline maker
- Product launch roadmap
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.