Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 18 tasks across 6 phases, about 7 weeks from start to finish with the parallel work shown.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Strategy | Launch goals and success metrics | 3 days | Day 1 | Nothing (starts first) |
| Strategy | Target customer and positioning | 7 days | Day 4 | Launch goals and success metrics |
| Strategy | Pricing and packaging decision | 7 days | Day 11 | Target customer and positioning |
| Product | Feature freeze | 1 day | Day 4 | Launch goals and success metrics |
| Product | Beta with selected customers | 20 days | Day 5 | Feature freeze |
| Product | Beta feedback fixes | 8 days | Day 25 | Beta with selected customers |
| Marketing | Messaging and launch narrative | 6 days | Day 11 | Target customer and positioning |
| Marketing | Launch page and pricing page | 8 days | Day 18 | Messaging and launch narrative, Pricing and packaging decision |
| Marketing | Demo video and screenshots | 7 days | Day 33 | Beta feedback fixes, Messaging and launch narrative |
| Marketing | Email and social campaign | 6 days | Day 26 | Launch page and pricing page |
| Marketing | Press and analyst briefings | 5 days | Day 17 | Messaging and launch narrative |
| Sales | Sales deck and battlecards | 6 days | Day 18 | Messaging and launch narrative, Pricing and packaging decision |
| Sales | Sales training | 3 days | Day 24 | Sales deck and battlecards |
| Support | Help center articles | 7 days | Day 33 | Beta feedback fixes |
| Support | Support team training | 2 days | Day 40 | Help center articles |
| Launch | Go/no-go review | 1 day | Day 42 | Sales training, Support team training, Demo video and screenshots, Email and social campaign |
| Launch | Launch day | 1 day | Day 43 | Go/no-go review, Press and analyst briefings |
| Launch | Post-launch review | 5 days | Day 44 | Launch day |
Durations are examples to replace with your own estimates, not benchmarks. Some work runs in parallel, so the plan takes 48 days instead of the 103 it would take one task at a time. The 9 darker bars are the critical path: a day lost on any of them moves the finish date.
About this product launch plan
A product launch is a relay between teams. Marketing cannot write the launch page until positioning is agreed, sales cannot be trained until pricing is final, and support cannot publish help articles until the beta has shown what customers get stuck on. This template puts each team in its own lane and draws those hand-offs as links, so a slip in one team shows up in every team that depends on it.
It is sized for a software or hardware product launching to existing customers and a wider market over about three months. The beta runs in parallel with content and enablement work, which keeps the plan short without skipping the feedback loop.
If your launch is a smaller feature release, delete the pricing and analyst tasks and shorten the beta. If it is a major launch with an event, add the event as its own milestone and link the press embargo to it.
Who it's for: Product managers and product marketing managers who coordinate a launch across several teams.
How to use it
- Use this template. Click Use this template. Each team opens as its own lane with the cross-team links drawn, so you can walk the plan with every team lead in one meeting.
- Set the launch date. Move the launch day to your real date and work backwards. If the go/no-go review lands before the beta fixes are done, the chart shows the conflict immediately.
- Assign owners per lane. Put one owner on every task. The weekly status view then groups open work by person, which is what a launch stand-up needs.
- Share a read-only link. Executives and partner teams can follow the plan from a link without an account.
The dependencies that decide your launch date
Two chains usually set the date. The first is the product chain: feature freeze, beta, beta fixes, then the demo video and help articles that need the finished product. The second is the commercial chain: positioning, pricing, then the sales deck and training. In this template the beta chain is the critical path, which matches most real launches: the product is ready later than the words about it.
The go/no-go review waits for sales training, support training, the demo video and the email campaign. It is a one-day task on purpose. Treat it as a gate where each lane confirms it is ready, and move the launch rather than launching with an unready support team.
Adapting it for a smaller or larger launch
For a feature launch to existing customers, drop pricing, press and analyst work and keep messaging, help articles and an in-app announcement. For a new product, add a waitlist or early-access phase before the beta and link the launch page to it so you can start collecting interest earlier.
Planning tips
- Freeze features before the beta, not after. Every change after the beta starts resets the documentation and the demo.
- Write the help articles from the beta feedback rather than from the spec; they will answer the questions customers really ask.
- Keep the post-launch review on the plan and invite every lane, so the next launch starts from what you learned.
- Hold the press briefings close to launch day and link them, so an embargo date never drifts away from the real launch.
Frequently asked questions
- How far in advance should I plan a product launch?
- For a new product, ten to fourteen weeks is common, which is roughly what this template shows. A feature launch to existing customers can often be planned in four to six weeks. Use your own team's history if you have it.
- What is the difference between this and the marketing launch template?
- The marketing launch template focuses on marketing's own work. This product launch plan gives product, marketing, sales and support their own lanes and links the hand-offs between them.
- Can I track the launch by team?
- Yes. Each phase opens as its own lane in the editor, and every task has an owner field. The dashboard view summarises progress, and the weekly status report lists what is done, in progress and at risk.
- Do the people I share the plan with need an account?
- No. Share links are read-only and open in any browser without an account.
Related templates and guides
- Marketing Launch Plan Gantt chart template
- Marketing Campaign Plan Gantt chart template
- Manufacturing New Product Introduction Gantt chart template
- Product Roadmap Gantt chart template
- Product launch roadmap
- Marketing campaign timeline maker
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.