Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 14 tasks across 4 phases, about 28 weeks if every task runs in sequence.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Prepare | Set up integration office and workstream leads | 5 days | Day 1 | Nothing (starts first) |
| Prepare | Day-one readiness checklist | 14 days | Day 6 | Set up integration office and workstream leads |
| Prepare | Employee and customer communications drafted | 7 days | Day 20 | Day-one readiness checklist |
| Prepare | Payroll and benefits continuity check | 3 days | Day 27 | Employee and customer communications drafted |
| Prepare | Essential system access for new staff | 5 days | Day 30 | Payroll and benefits continuity check |
| Day one | Deal close and announcement | 1 day | Day 35 | Essential system access for new staff |
| Day one | Day-one support desk | 5 days | Day 36 | Deal close and announcement |
| Integrate | Organization design and role mapping | 21 days | Day 41 | Day-one support desk |
| Integrate | Finance and reporting alignment | 30 days | Day 62 | Organization design and role mapping |
| Integrate | IT systems and email consolidation | 45 days | Day 92 | Finance and reporting alignment |
| Integrate | Customer and vendor contract transition | 30 days | Day 137 | IT systems and email consolidation |
| Stabilize | Policy and process harmonization | 21 days | Day 167 | Customer and vendor contract transition |
| Stabilize | Synergy tracking review | 5 days | Day 188 | Policy and process harmonization |
| Stabilize | Integration close-out and lessons learned | 3 days | Day 193 | Synergy tracking review |
Durations are examples to replace with your own estimates, not benchmarks. Every task waits for the one before it, so the whole chain is the critical path until you overlap work that can run in parallel.
About this merger integration plan
Integration work splits into two phases: what must be ready on the day the deal closes, and what can be merged over the months after. This plan puts day-one readiness first — communications, payroll continuity, access to essential systems — and then sequences the longer workstreams.
It fits a small or mid-sized acquisition. Larger deals usually run each workstream as its own plan; use this as the integration office's summary view.
Who it's for: Integration leads, operations executives, corporate development teams and advisors.
How to use it
- Open the plan. Click Use this template. The integration plan loads as a live Gantt chart.
- Name workstream owners. Put a single owner on each row; integration stalls when workstreams are owned by committees.
- Flag risks early. Set a task's status to At risk when a dependency such as a data export or contract consent is late.
- Share with leadership. Send a read-only link for steering meetings instead of rebuilding slides each week.
Planning tips
- Keep day-one scope small: continuity first, optimization later.
- Plan communications for employees before customers hear about the deal elsewhere.
- Track synergy targets against the dates they depend on.
Frequently asked questions
- What is day-one readiness?
- The minimum set of things that must work when the deal closes, such as payroll, communications and access to essential systems.
- How long does integration take?
- It varies widely with deal size. This template totals a little over six months if every task runs in sequence; workstreams usually overlap.
- Is the plan confidential?
- Share links are read-only and only people with the link can open them. Don't share deal details beyond the people who need them.
Related templates and guides
- ERP Implementation Plan Gantt chart template
- Office Move Plan Gantt chart template
- Strategic Planning Process Gantt chart template
- Smartsheet alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.