Free, no sign-up to start: the plan opens as a live, editable Gantt chart. 14 tasks across 6 phases, about 21 weeks from start to finish with the parallel work shown.
What's in the template
| Phase | Task | Duration | Starts | Depends on |
|---|---|---|---|---|
| Strategy | Vision, goals and success measures | 10 days | Day 1 | Nothing (starts first) |
| Strategy | Roadmap workshop with workstream leads | 3 days | Day 11 | Vision, goals and success measures |
| Governance | Gate 1: funding approved | 1 day | Day 14 | Roadmap workshop with workstream leads |
| Process | Map current processes | 15 days | Day 15 | Gate 1: funding approved |
| Process | Redesign priority processes | 25 days | Day 30 | Map current processes |
| Technology | Choose the platform | 20 days | Day 15 | Gate 1: funding approved |
| Technology | Build and configure | 45 days | Day 35 | Choose the platform |
| People | Change and communications plan | 10 days | Day 15 | Gate 1: funding approved |
| People | Train managers and champions | 15 days | Day 55 | Change and communications plan, Redesign priority processes |
| Governance | Gate 2: ready for rollout | 1 day | Day 80 | Build and configure, Train managers and champions |
| Rollout | Pilot with one region or team | 20 days | Day 81 | Gate 2: ready for rollout |
| Rollout | Full rollout | 40 days | Day 101 | Pilot with one region or team |
| Rollout | Retire the old way of working | 10 days | Day 141 | Full rollout |
| Governance | Gate 3: benefits review | 1 day | Day 141 | Full rollout |
Durations are examples to replace with your own estimates, not benchmarks. Some work runs in parallel, so the plan takes 150 days instead of the 216 it would take one task at a time. The 9 darker bars are the critical path: a day lost on any of them moves the finish date.
About this project roadmap
A project roadmap sits above the project plan. It shows the big pieces of work over months, how they relate and where the decisions are, without the task-level detail. Leaders use it to see whether the whole programme hangs together; teams use it to see where their work fits.
This template is for an organisation-wide change with process, technology and people workstreams, such as moving to a new operating model or replacing a core system. Three decision gates mark where the programme commits money and where it checks results. The workstreams run in parallel between gates, and the links show the real dependencies: managers cannot be trained on processes that have not been redesigned yet, and the rollout cannot start until all three workstreams are ready.
A product roadmap is different: it plans features and releases for a product, and there is a separate product roadmap template for that. Use this one when the roadmap is for a programme of change rather than a product.
Who it's for: Programme managers, PMO leads and executives planning a multi-team initiative over one or two quarters.
How to use it
- Use this template. Click Use this template. Each workstream opens as a lane with the gates in their own lane, so the decision points stand out.
- Name your workstreams. Replace process, technology and people with your own workstreams. Three to six is a readable number; more than that usually means two roadmaps.
- Draw the cross-workstream links. For each workstream ask what it needs from the others, and link those bars. These links are what a roadmap adds over separate team plans.
- Review it at every gate. At each gate, update durations from what has really happened and look at where the finish date has moved. Share a fresh read-only link after each review.
Keep a roadmap at roadmap level
Bars on a roadmap should be weeks or months long. If a bar is a three-day task, it belongs in a team plan. Keeping the roadmap coarse is what lets it fit on one screen and stay true for longer; each workstream can keep its own detailed plan underneath.
The gates are what make the roadmap a management tool rather than a picture. Gate 1 commits funding, gate 2 checks that every workstream is ready before people are asked to change how they work, and gate 3 checks whether the change delivered what the vision promised.
Where this roadmap is tight
The critical path runs through choosing the platform and building it. The process and people workstreams have slack because they finish before the build does. That slack is useful: it is the time to involve more people in the process redesign, or to train champions more thoroughly.
If the platform choice takes longer than planned, everything after gate 2 moves. That is worth saying out loud at the first steering meeting, and it is easy to show by dragging the bar and letting the chart move the dates.
Planning tips
- Show the roadmap in months to executives. The same chart in weeks is for workstream leads.
- Put gates in their own lane so they are easy to find and impossible to quietly skip.
- Give every workstream one accountable lead and write their name on its bars.
- Revisit the roadmap at each gate rather than on a fixed calendar. Gates are where you learn something new.
Frequently asked questions
- What is a project roadmap?
- A high-level view of a project or programme over time: the main workstreams, their timing, the dependencies between them and the key decision points. It shows direction and sequence rather than individual tasks.
- What is the difference between a project roadmap and a product roadmap?
- A product roadmap plans features and releases for a product. A project roadmap plans the workstreams and decisions of a piece of change, such as a reorganisation or a system replacement. This site has a separate product roadmap template.
- How is a roadmap different from a project plan?
- A roadmap is the summary: a few long bars and decision gates. A project plan has the tasks, owners, budget and risks. Many teams keep a roadmap for leaders and a plan for each workstream.
- Can I present this roadmap in PowerPoint?
- On the Solo plan, the editor downloads the chart as a PowerPoint file, an image or a PDF. The CSV download on this page is free and opens in any spreadsheet.
Related templates and guides
- Product Roadmap Gantt chart template
- Strategic Planning Process Gantt chart template
- Project Plan Gantt chart template
- Merger Integration Plan Gantt chart template
- Smartsheet alternative
- Free Gantt chart maker, no sign-up
- Critical path calculator
- Free timeline templates
- All Gantt chart templates
- Gantt chart examples
- How to make a Gantt chart
- Excel Gantt chart template
The free plan saves one project. Downloads from the editor (PDF, CSV) and more projects are on Solo, $12/month.